• 1
    Select (single click) the project name on the Outline.
  • 2
    Select the three-dot menu.
  • 3
    Select View Properties.
  • 4
    The Properties panel will open on the right side of the Stage. In the Organization section is a setting, "Is a Baseline:" (You may need to scroll to see this setting.) Select the checkbox for Is a Baseline.
  • 5
    Select Update.
  • 6
    The Properties panel will close. To use the Baseline to start a new project, select the New Project quicklink in the upper left corner.
  • 7
    Select Baselines.
  • 8
    The Baseline project now appears as an option here. Select the baseline.
  • 9
    On the New Project From Baseline panel, rename the project. For this exercise, select the name field and we'll add a name.
  • 10
    Selecting Keep Asignments will mean that any authors or reviewers assigned to the original Baseline will be assigned to the new project. Select Duplicate Project.
  • 11
    The new project will open.